2014-08-11 KFDM Project Management Meeting Notes

Date

Attendees

Goals

  • Review Project Status including Issues, Risks, and Budget

Discussion items

TimeItemWhoNotes
5 minStatus of Project ResourcesPam
    Sowmya & Reasat progress evaluation: pairing is working well. Sowmya is every bit as good as we'd hoped.
    With Sowmya taking lead, some of the pressures that have developed between modelers ands ETL are easing.

 

10 minSchedule Status Pam 
  • we are gaining steady momentum with addition of Sowmya
  • RSP DIM rework seems to have slowed and focus is now on new development
  • Role DIM is really 6 DIMs - very complete.  ETL are teaming up on it. Estimate provided for completion = 15 days but progress is already ahead of that.
  • Bruce has vowed to complete the report specs early (by end of Sep) 
10 minReview of Issues and Risks Pam 
  • Issue 2 can be updated to resolved as there are no additional changes planned to the current ETL developers 

Action items

  •