2014-07-17 KFDM Weekly Management Meeting notes
Date
Attendees
- Brett Paulson
- Former user (Deleted) Mackey - IBI
- Rob Boncoddo
- Former user (Deleted) - HEBi
Goals
KIM Star Project Status Update
Discussion items
Time | Item | Who | Notes |
---|---|---|---|
5 min | Project Schedule | Pam | ~4 weeks behind schedule - ETL resource constraints and iterative test and remediate activities on DIMs. Effort estimates adjusted (increased) to accommodate discovered anomalies and complexity - estimates doubled on most cases.
|
5 min | Resource Challenges / update on Consultant search | Pam | Consultant from Hallmark Tech secured for Aug-Oct. Reasat will be extended 1 week for KT (Aug 4-8) |
5 min | Project Budget Update | Brett | budget is on track - delays are not expected to impact budget at this time (internal resources). UITS is picking up the tab for additional ETL contract |
5 min | Impact of delays on HEBI | Pam | Steve noted that 3-4 week schedule delays will not impact HEBI's availability - he is prepared to reschedule his support from August to September |
Action items
Former user (Deleted)  -  provide updated schedule of hours for non-KIM star tasks resulting from delays experienced on HEBI side.