Copy of 2014-07-17 KFDM Weekly Management Meeting notes

    • Date

Attendees

Goals

  • KIM Star Project Status Update

Discussion items

TimeItemWhoNotes
5 minProject SchedulePam

~4 weeks behind schedule - ETL resource constraints and iterative test and remediate activities on DIMs.

Effort estimates adjusted (increased) to accommodate discovered anomalies and complexity - estimates doubled on most cases.

  • result is the first Fact table will not be completed until early Sep - impacts contracted support from HEBI? 
5 minResource Challenges / update on Consultant search Pam Consultant from Hallmark Tech secured for Aug-Oct. Reasat will be extended 1 week for KT (Aug 4-8)
5 min Project Budget UpdateBrett 

budget is on track - delays are not expected to impact budget at this time (internal resources). 

UITS is picking up the tab for additional ETL contract

5 min Impact of delays on HEBI Pam 

Steve noted that 3-4 week schedule delays will not impact HEBI's availability -

he is prepared to reschedule his support from August to September

Action items

  • Former user (Deleted)  -  provide updated schedule of hours for non-KIM star tasks resulting from delays experienced on HEBI side.