Amano Garage Parking and Gates System Upgrade
Milestones
Activity | Status | Planned Date | Comments |
---|---|---|---|
Install Updated Readers | COMPLETE | Â Â | Need revised schedule. Requirement for IO 100 added and IP addresses - Complete |
Replace Gates, card readers, ticket dispenser, cards | COMPLETE | Â Â | Need revised schedule. Requirement for IO 100 added and IP addresses - Complete |
New Server: Card Access Control and revenue reports | COMPLETE |   | Adjusted based on Card set up. New Planned completion is 6/21/19 |
Facilities Support South Garage for Spring Break | COMPLETE | Â | |
Set up Account with Payment Express | COMPLETE | Closing in on finalizing the contract. May not be ready for 5/14/19. Completed 5/31/19 (late) | |
Gated Lots:
| COMPLETE | Issue with communication to server. Gate will work without the network connection. | |
Stamford Garage | MOVED | Moved to UPDC coordination |
Tasks
Detail | Status | Completion Date | Notes |
---|---|---|---|
| COMPLETE | Â Â | Completed as requested |
| COMPLETEÂ | Â Â | |
| COMPLETE | Â Â | |