Amano Garage Parking and Gates System Upgrade

Project NameAmano Garage and Gates Upgrade
Project Phase

CLOSED

Target Go Live

 

Due Date

 

Kick Off

 

Project ManagerGeorge Perron
Technical Lead
Functional PartnerFacilities / Parking Services
Functional LeadDwight Atherton


Milestones

ActivityStatusPlanned DateComments
Install Updated Readers

COMPLETE

  

Need revised schedule. Requirement for IO 100 added and IP addresses - Complete
Replace Gates, card readers, ticket dispenser, cards

COMPLETE

  

Need revised schedule. Requirement for IO 100 added and IP addresses - Complete

New Server: Card Access Control and revenue reports

COMPLETE

  

Adjusted based on Card set up.  New Planned completion is 6/21/19

Facilities Support South Garage for Spring Break

COMPLETE

 


Set up Account with Payment Express

COMPLETE


Closing in on finalizing the contract.  May not be ready for 5/14/19. 

Completed 5/31/19 (late)

Gated Lots:

  • Budds
  • Hilltop
  • Wilbur Cross

COMPLETE


Issue with communication to server. Gate will work without the network connection.
Stamford Garage

MOVED


Moved to UPDC coordination


Tasks

DetailStatusCompletion DateNotes
  • Facilities cut hole for larger reader in South Garage
     

COMPLETE

  

Completed as requested
  •  Facilities Adjust conduit
COMPLETE 

  


  •  Facilities seal installed box

COMPLETE