Date
Attendees
- Former user (Deleted)
- Brett Paulson
- Former user (Deleted)
- Sowmya Mallikarjuna
Goals
Project Status and schedule review
Discussion items
Time | Item | Who | Notes |
---|---|---|---|
5 min | General announcements | Pam | Linda on vacation rest of this week. This should not impact progress however since current tasks are with Role DIM Rob is out of the office today as well |
10 min | Project Status | Pam | Gaining steady momentum with Sowmya onboard - tasks are on track Bruce feels he will beat his original goal to have reports specs complete by end of Sep. Central report specs expected complete this week %complete values updated on appropriate tasks |
15 min | Ideas for additional acceleration | All | Is there anything in the schedule that can begin early to recapture time?
|
Action items
Former user (Deleted) - redistribute updated project schedule