Reasat Chowdhury has been extended through September. He will assume Jr ETL role
Validation activities
Rework on DIMs resulting from validation
production issues
Sowmaya Mallikunarjuna joins us on Monday Aug 11. She will be here through October and will assume lead ETL role.
Interviews begin this week for perm positions
5 min
Project Schedule
Pam Kriedeman
Ngozi has requested that we review the project schedule and find opportunities to accelerate so that we can complete it by the end of October.
10 min
Project Budget
Brett Paulson
Budget adjusted to reflect the extension of Reasat's contract.
Brett reports that the above adjustment came from the contingency and therefore all should be aware that we have less contingency to support additional slippage
5 min
HEBI Additional tasks
Pam Kriedeman
Process for managing production issues found during other authorized "other" activites