-Added a check for the Stage action buttons to confirm the PDF is downloaded prior to the web form being submitted.


2020/04/08

-Added form storage for uploading signed and initialed PDFs

-updated email notifications to include PDFs

-updated instructions for modified process

-Added additional logic to prevent unfinished PDF downloads or form submission


Field Mapping for PDF



PDF Field Name

var

Leap var (use var column instead)

Leap Field ID

Leap Field Title

1

Month Ending

monthEnding

monthEndCalYear

F_MonthEndCalYear

Combined Month Ending and Calendar Year

2

Contractor Name

companyName

contractorName

F_ContractorName

General Contractor Name

3

Project Name

projectName

projectName

F_ProjectName

Project Name

4

Awarding Agency Name

awardingAgencyName

contractAwardAgency

F_ContractAwardAgency

F_ContractAwardAgency

5

Project Number

projectNumber

projectNumber

F_ProjectNumber

Project Number

6

Is Contractor an S/MBE? What is DAS Class?

smbe

vendorCertClass

F_VendorCertClass

Certification Class

7

Actual Project Mobilization Date

mobilizationDate

mobilizationDate

F_MobilizationDate

Actual Project Mobilization Date

8

Project Value

projectValue

projectValue

F_ProjectValue

Project Value

9

Percent Completed to Date

percentComplete

percentCompleteToDate

F_PercentCompleteToDate

Percent Completed To Date

10

Is this a FINAL Report?

finalReport

isFinalReport

F_IsFinalReport

Is This a Final Report?

11

Estimated Completion Date

completionDate

estCompletionDate

F_EstCompletionDate

Estimated Completion Date

12

Report Entry Date

reportEntryDate

reportEntryDate

F_ReportEntryDate

Report Entry Date

13

Printed Name and Printed Title of Person Signing

printedAuthorizedSignature

signerName

F_SignerName

Signer Name & Title

14

Month Ending

Same as above

monthEndCalYearBottom

F_MonthEndCalYear

Combined Month Ending and Calendar Year

15

Contractor Name

Same as above

contractorNameBottom

F_ContractorName

General Contractor Name

16

Project Name

Same as above

projectNameBottom

F_ProjectName

Project Name

17

Project Number

Same as above

projectNumberBottom

F_ProjectNumber

Project Number

18

S/MBE Contractor Textbox

TBD

smbeTableAsText

F_SmbeTableAsText

SMBE Table As Text

19

S/MBE Contractor Name

contractorName


F_SubtierCompany

Sub-Tier Company

20

DAS Class

dasClass


F_SubtierDasClass

DAS Class

21

Total Contract Amount

totalContractAmount


F_TotalContractAmount

Total Contract Amount

22

Total Payment this Month

totalPaymentThisMonth


F_TotalMonthlyPayment

Total Payment this Month

23

Total Payment to Date

totalPaymentToDate


F_TotalPaymentToDate

Total Payment to Date

24Page Numbers #1 and #2**generated from Process**


25Initials**physically filled by person submitting form**


...