ActivityStatusPlanned DateComments
Install Updated Readers

Status
colourBlue
titleCOMPLETE

  

Need revised schedule. Requirement for IO 100 added and IP addresses - Complete
Replace Gates, card readers, ticket dispenser, cards

Status
colourBlue
titleCOMPLETE

  

Need revised schedule. Requirement for IO 100 added and IP addresses - Complete

New Server: Card Access Control and revenue reports

Status
colourYellowBlue
titleIN PROCESScomplete

  

Adjusted based on Card set up.  New Planned completion is 6/21/19

Facilities Support South Garage for Spring Break

Status
colourBlue
titleCOMPLETE

 


Set up Account with Payment Express

Status
colourBlue
titleCOMPLETE


Closing in on finalizing the contract.  May not be ready for 5/14/19. 

Completed 5/31/19 (late)

Gated Lots:

  •  Budds
  •  Hilltop
  •  Wilbur Cross

Status
colourBlue
titleCOMPLETE


Issue with communication to server. Gate will work without the network connection.
Stamford Garage

Status
colourYellowBlue
titleON HOLDMoved


Moved to UPDC coordination


Tasks

DetailStatusCompletion DateNotes
  •  Facilities cut hole for larger reader in South Garage
     

Status
colourBlue
titleCOMPLETE

  

Completed as requested
  •   Facilities Adjust conduit
Status
colourBlue
titleCOMPLETE
 

  


  •   Facilities seal installed box

Status
colourBlue
titleCOMPLETE

  






...