Pre-Release
- 06 2016 (Release-14 days)Notify testers of issues in UAT that are ready to be tested. Richard Ritchie
- (Release-9 days)Email notification to developers for code freeze. Richard Ritchie
- (Release-8 days)Code Freeze (End of Business). Richard Ritchie
- (Release-8 days)Verify origin/master has code from any tagged versions since last major release. Richard Ritchie
- (Release-7 days)Create Footprints RFC (XXXX). Richard Ritchie
- 13 2016 (Release-7 days)Mark RFC (XXXX) as Functionally Approved. Former user (Deleted)
- 13 2016 (Release-7 days)Create JIRA Task for Tag Tag and Deploy (KPS-XXX). Assign to Ben. Richard Ritchie 13
- 2016 (Release-7 days)Create JIRA Task for Deploy (KPS-XXX). Assign to BenNotify testers of issues in UAT that are ready to be tested. Richard Ritchie
- (Release-7 days)Notify users of upcoming release. Brett Paulson
- (Release-6 days)Email notification to developers for code freeze. Richard Ritchie
- 13 2016
(Release-
7 days)Final UAT Deployment Benjamin Daniels5 days)Development Team Code Review. Richard Ritchie, Kathleen Avery (Deactivated), David Chudnow (Deactivated), Paul Morano
(Release-5 days)Code Freeze (End of Business). Richard Ritchie
- 2016
(Release-
7 days)Notify testers of issues in UAT that are ready to be tested4 days)Verify origin/master has code from any tagged versions since last major release. Richard Ritchie
- 2016 (Release-7 4 days)Notify users of upcoming release. Brett PaulsonFinal UAT Deployment Paul Morano
- Richard Ritchie (Release-1 day)Change JIRA issues status to "READY FOR PROD".
- 19 2016 (Release-1 day)Tag the scheduled Release. Richard Ritchie
- 19 2016 (Release-1 day)Build the Build the scheduled Release. Benjamin Daniels
- (Release-1 day)Create Pull Requests for SQL changes. Richard Ritchie
- (Release-1 day)Deploy to SUP environment in afternoon. Benjamin Daniels
Release 20 2016 (Verify this date does not conflict with semester moratoriums. http://itstatus.uconn.edu/ )
- Perform Deployment. 6:30-7:00 a.m. Benjamin Daniels
- Change JIRA issues status to "PROD DEPLOYMENT COMPLETE". Benjamin Daniels
- Release the new version in JIRA. Benjamin Daniels
- Brett Paulson, Jean Ose Perform Checkout
- Brett Paulson Notify Users with release notes and dates data will be refreshed.
- Change JIRA issues status to "CLOSED" Richard Ritchie
Post-Release
- 22 2016 (Release+2 days)Database refresh. Richard Ritchie
- 22 2016 (Release+2 days)Re-Encrypt data. Richard Ritchie
- 27 2016 (Release+7 days)Monthly Kuali Audit Report. Kathleen Avery (Deactivated)
...