- 01 Mar (Release-14 days)Notify testers of issues in UAT that are ready to be tested. Richard Ritchie
- 08 Mar (Release-7 days)Create Footprints RFC (XXXX). Richard Ritchie
- 08 Mar (Release-7 days)Mark RFC (XXXX) as Functionally Approved. Former user (Deleted)
- 08 Mar (Release-7 days)Create JIRA Task for Tag and Deploy (KPS-XXX). Assign to Ben. Richard Ritchie
- 08 Mar (Release-7 days)Development Team Code Review. Richard Ritchie, Kathleen Avery (Deactivated), David Chudnow (Deactivated), Paul Morano (Release-7 days)Notify testers of issues in UAT that are ready to be tested. Richard Ritchie
- (Release-7 days)Final UAT Deployment Paul Morano 08 Mar (Release-7 days)Notify users of upcoming release. Brett Paulson
- 09 Mar (Release-6 days)Email notification to developers for code freeze. Richard Ritchie
-
10 Mar (Release-5 days)Development Team Code Review. Richard Ritchie, Kathleen Avery (Deactivated), David Chudnow (Deactivated), Paul Morano
(Release-5 days)Code Freeze (End of Business). Richard Ritchie
-
10 Mar (Release-5 4 days)Verify origin/master has code from any tagged versions since last major release. Richard Ritchie
- Mar (Release-4 days)Final UAT Deployment Paul Morano
- Richard Ritchie (Release-1 day)Change JIRA issues status to "READY FOR PROD".
- 14 Mar (Release-1 day)Tag the scheduled Release. Richard Ritchie
- 14 Mar (Release-1 day)Build the scheduled Release. Benjamin Daniels
- 14 Mar (Release-1 day)Create Pull Requests for SQL changes. Richard Ritchie
- 14 Mar (Release-1 day)Deploy to SUP environment in afternoon. Benjamin Daniels
Release 15 Mar (Verify this date does not conflict with semester moratoriums. http://itstatus.uconn.edu/ )
- Perform Deployment. 6:30-7:00 a.m. Benjamin Daniels
- Change JIRA issues status to "PROD DEPLOYMENT COMPLETE". Benjamin Daniels
- Release the new version in JIRA. Benjamin Daniels
- Perform Checkout Brett Paulson, Jean Ose
- Notify Users with release notes and dates data will be refreshed. Brett Paulson
- Change JIRA issues status to "CLOSED" Richard Ritchie
Post-Release
- 17 Mar (Release+2 days)Database refresh. Richard Ritchie
- 17 Mar (Release+2 days)Re-Encrypt data. Richard Ritchie