Milestone | % Complete% Compleye | StatusStay |
---|
KFS 5.3 sandbox environment for Fit-Gap | 80% | Status |
---|
colour | YellowGreen |
---|
title | In ProgressComplete |
---|
|
|
Project Kickoff | 0% | Status |
---|
colour | Green |
---|
title | ScheduledComplete |
---|
|
|
Fit-Gaps | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
KFDM Impact Analysis | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
KFDM ETL Code Changes | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
Migration of 4.1 Required Modifications | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
Remediation of other gaps (not 4.1. mods) | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
Migration of 4.1 Interfaces | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
End to End User Acceptance testing | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
| |
Documentation & Training | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
Load testing | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
KFS Year end close in 4.1 | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
Production Readiness Planning & Assessment | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
Go-Live Approval | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|
Cutover in PRD | 0% | Status |
---|
colour | Green |
---|
title | Scheduled |
---|
|
|